| Line 57: | Line 57: | ||
| Our team concentrated on creating a complete packaging solution for the project during this week. To ensure the product' | Our team concentrated on creating a complete packaging solution for the project during this week. To ensure the product' | ||
| ==== 13th Week Report ==== | ==== 13th Week Report ==== | ||
| + | During this week we focused on starting writing the user manual. Additionally, | ||
| ==== 14th Week Report ==== | ==== 14th Week Report ==== | ||
| ===== Meetings ===== | ===== Meetings ===== | ||
| Line 215: | Line 216: | ||
| === Minute: === | === Minute: === | ||
| + | We started the meeting by showing the progression of the code. Then we received feedback on our paper and received help in some aspects regarding it. Next, we discussed our user manual, which still needs some finishing and shortening of the text. | ||
| ==== 16th Meeting | ==== 16th Meeting | ||
| === Agenda: === | === Agenda: === | ||
| Line 237: | Line 238: | ||
| |22 Mar.2023 |29 Mar.2023 |Technical drawings and system schematics |We have to make engineering drawings of our product and its elements and make system schematics. | Whole team | | |22 Mar.2023 |29 Mar.2023 |Technical drawings and system schematics |We have to make engineering drawings of our product and its elements and make system schematics. | Whole team | | ||
| |29 Mar.2023 |16 Apr.2023 |Interim presentation |We are preparing the report and presentation for the interim presentation. | Whole team | | |29 Mar.2023 |16 Apr.2023 |Interim presentation |We are preparing the report and presentation for the interim presentation. | Whole team | | ||
| + | |16 Apr.2023 |17 May.2023 |Correction of the report |Based on the feedback from the supervisors we updated the report. |AF, FL | | ||
| + | |20 Apr.2023 |26 Apr.2023 |Final list of materials |We did research on materials available for our project and their suppliers to make a final list of materials needed for the prototype. |Whole Team | | ||
| + | |20 Apr.2023 |26 Apr.2023 |Leaflet |We created a leaflet for our product. |Whole Team | | ||
| + | |20 Apr.2023 |26 Apr.2023 |3D model video |Our team members started to work on 3D model video of the product. |LH, AT | | ||
| + | |20 Apr.2023 |26 Apr.2023 |Flyer |A flyer for our product was created. |LH | | ||
| + | |27 Apr.2023 |03 May.2023 |Materials and prices |Based on the final list of materials, we bought components for the prototype. |LH, AT | | ||
| + | |27 Apr.2023 |03 May.2023 |Solidworks model |The Solidworks model was adjusted. |LH | | ||
| + | |27 Apr.2023 |03 May.2023 |Packaging |Started the work on packaging. |EB | | ||
| + | |27 Apr.2023 |03 May.2023 |Assembly of final product |Final product was assembled. |AT | | ||
| + | |27 Apr.2023 |17 May.2023 |Work on software |Started work on software. |SS | | ||
| + | |04 May.2023 |17 May.2023 |Paper |Started to work on the article of our project. |AF, FL | | ||
| + | |04 May.2023 |17 May.2023 |Mechanisms for prototype |Started to work on mechanisms of the lower parts of the prototype. |FL, LH | | ||
| + | |04 May.2023 |17 May.2023 |User journey |Created the user journey. |LH | | ||
| + | |18 May.2023 |24 May.2023 |Final packaging solution |Finalized the packaging solution. |EB | | ||
| + | |18 May.2023 |24 May.2023 |Presentation for marketing |We worked on and presented our marketing plan. |Whole Team | | ||
| + | |25 May.2023 |31 May.2023 |Adjust marketing |Some of the aspects of the marketing plan were adjusted. |AF | | ||
| + | |25 May.2023 |31 May.2023 |Finish 3D model video |3D model video was finalized. |LH | | ||
| + | |25 May.2023 |07 Jun.2023 |User manual |We created a user manual. |Whole Team | | ||
| + | |01 Jun.2023 |07 Jun.2023 |Poster |Created the poster. |LH | | ||
| + | |01 Jun.2023 |07 Jun.2023 |Software development |Software development. |SS | | ||
| + | |01 Jun.2023 |07 Jun.2023 |Packaging for gas-lift |Created packaging for the gas-lift. |EB | | ||
| + | |01 Jun.2023 |07 Jun.2023 |Paper |Adjusted the paper with new data and some corrections. |AT, AF, FL, LH | | ||